Realistic Project Timeline.

Naive vs realistic estimates by project stage, and why each gap exists.

  • Data collection and annotation — naive: 2 weeks · realistic: 4–8 weeks · class ambiguity, quality issues, coverage gaps
  • Baseline model training — naive: 1 week · realistic: 1–2 weeks · relatively predictable
  • Iteration to production quality — naive: 1 week · realistic: 4–8 weeks · multiple training cycles, augmentation, evaluation
  • Evaluation and validation — naive: 2–3 days · realistic: 1–2 weeks · per-class analysis, qualitative review, edge case testing
  • Integration and deployment — naive: 1 week · realistic: 2–4 weeks · pre-processing pipeline, format conversion, system integration
  • Total — naive: 5–6 weeks · realistic: 12–24 weeks · 2–4× the naive estimate